Project Proposal for Immediate Ecological Restoration

Objectives of the project :

To begin preparatory work for the restoration of the coastal belt in the Auroville tsunami rehabilitation programme area.

This micro-project will serve as a pilot project for a proposed two-year ecological restoration project to be carried out in the programme area. Preliminary investigations will be carried out into the options available for an ecological restoration project in the area. The micro-project will allow nursery work to begin as well as initial participatory land use mapping to take place.

  1. Planned activities :

A number of these activities already began in February in order to avoid missing an important window of opportunity for seed collection during this period of the year. In addition, plans are under way to begin the participatory land use exercises, with formal contact already made with all of the Paalams. The activities outlined above will provide the necessary feedback to inform the drawing up of the two-year project.

  1. Output:
  1. Human Resources :

The team that will carry out this preparatory work is newly formed and currently consists of the following people:

  1. Budget:

Item

Unit Cost

No of Unit

Total Budget in RS

 

 

 

 

Project Goods and Services

 

 

 

Field helper

3,500

1

3,500

Nursery workers

3,000

2

6,000

Seed collectors

3,000

1

3,000

Transport - seed collection

1,200

4

4,800

Transport - survey

700

5

3,500

Tea and snacks

100

9

900

Planting bags (per kg)

70

120

8,400

Top soil

300

1

300

Hosepipe

1,800

1

1,800

PRA materials

1,000

1

1,000

Field staff transport

500

5

2,500

Sub-Total

 

 

35,700

 

 

 

 

Staff Cost

 

 

 

Project coordinator

8,000

2

16,000

Botanist

12,000

1

12,000

Surveyor

5,000

1

5,000

Office worker

3,000

1

3,000

Administrator

3,500

1

3,500

Networker / social worker

6,500

1

6,500

Sub Total

 

 

46,000

 

 

 

 

Administration

 

 

 

Electricity / phone

1,000

1

1,000

Stationary

1,000

1

1,000

Office running costs

4,000

1

4,000

Contingencies

500

3

1,500

Sub Total

 

 

7,500

Total Budget

 

 

89,200